Meeting Minutes
April 1, 2015
- Finalized testing methods
March 2015
- Manufactured device and testing frame
- Formulated testing method
February 27, 2015
- NEBEC paper revisions and submission
February 22, 2015
- NEBEC Paper
- Drawings for machine shop
February 17, 2015
- Optimization of design
- Testing apparatus and methodology
February 10, 2015
- Optimization of design
- Testing apparatus design and methodology
February 6, 2015
- Discussed/determined various testing methods
- Discussed optimization of design results
February 3, 2015
- Update on testing methods
- Worked on optimization of design
December 9, 2014
- Completed/Submitted SP1 Final Report
December 7, 2014
- Revised/edited SP1 Final Report
December 2, 2014
- Looked for companies to order screws from
- Reviewed presentation for Design Review
December 1, 2014
- Finalized presentation for the End of Semester Design Review
November 30, 2014
- Created outline of End of Semester Design Review presentation
- Confirmed testing methods and equipment to be used
November 25, 2014
- Completed final drawings of the arch bars (with dimensions/tolerancing)
- Completed writing and formatting of rough draft of final report
November 17, 2014
- Reviewed completed portions of report draft
- Delegated some of the remaining portions of report
- Completed final drawings of the VMM plates (with dimensions/tolerancing)
November 13, 2014
- Further finalized budget
- Created a preliminary outline for the Final Report
November 11, 2014
- Worked on finalizing the project budget
- Revised website for review
November 3, 2014
- Worked on verification and validation of requirements/specifications
- Analyzed new structural design ideas modeled in SolidWorks
October 29, 2014
- IDR presentations
October 28, 2014
- Review IDR presentation slides
October 27, 2014
- Finalized IDR presentation slides
October 24, 2014
- Continuation of creating IDR presentation slides
- Worked on the structural design of the device
October 23, 2014
- Formulated Interim Design Review (IDR) presentation outline
- Added verification and validation to each design requirement
- Analyzed Finite Element Analysis data
- Worked on structural design of device
October 17, 2014
- Calculated and determined maximum force acting on the jaw
- Analyzed Finite Element Analysis data
October 8, 2014
- Worked on structural design of the device
October 5th 2014
- Finalized rough draft of the Budget
October 3rd 2014
- Completed Travel Request Form for NEBEC
October 2nd 2014
- Structural design of the device
- Forces within the mouth/acting on the jaw
September 30th 2014
- Met with Joe Zanetti to discuss preparation for using the machine shop
September 29th 2014
- Completed the safety class and test and became qualified to work in the machine shop
September 26th 2014
- Briefly met with Joe Zanetti to discuss using the machine shop
- Set up an official meeting time with Joe Zanetti
September 23rd 2014
- Completed realistic constraints assignment
September 21st 2014
- Began realistic constraints assignment
- Developed multiple structural design ideas of device
September 17th 2014
- Detailed explanation of BSSO Procedure
- Revisions to design requirements/specifications
- Began planning individual tasking – Gantt Chart
September 11th 2014
- Creation of team website
- Revisions to design requirement/specifications presented
September 9th 2014
- Finalized and practiced presentation
September 7th 2014
- Further developed design requirements/specifications
- Began writing PowerPoint slides for presentation
September 5th 2014
- Discussed presentation outline & design requirements/specifications with advisor
September 4th 2014
- Continuation of writing requirements/specifications based on previous research
- Modification of preliminary requirements/specifications presented in senior project seminar
September 1st 2014
- Began formulation of design requirements/specifications
August 28th 2014
- Group discussion of research findings
- Delegation of further research topics between group members